Simulation of Construction Project Duration
- 1 June 1979
- journal article
- Published by American Society of Civil Engineers (ASCE) in Journal of the Construction Division
- Vol. 105 (2) , 117-128
- https://doi.org/10.1061/jcceaz.0000827
Abstract
MUD (model for uncertainty determination) will simulate the progress under uncertainty of the typical construction project on which the activity durations are not independent of each other. Monte Carlo simulation models the effects of uncertainties that are independent of calendar date. Daily progress under uncertain weather is simulated using historical weather data. Activity criticalities are computed for the simulated activity times. The samples from multiple simulations of a project are combined by MUD to calculate a range estimate (mean and standard duration) for activity and project durations, times, and criticality. A small example project illustrates some of the capabilities of MUD.Keywords
This publication has 0 references indexed in Scilit: