Scheduling project networks
- 1 April 1967
- journal article
- Published by Association for Computing Machinery (ACM) in Communications of the ACM
- Vol. 10 (4) , 225-231
- https://doi.org/10.1145/363242.363264
Abstract
Some of the basic concepts and terminology of project networking are developed. The Critical Path Algorithm in. corporated in the C-E-I-R proprietary scheduling system RAMPS (Resource Allocation and Multi-Project Scheduling) is described. The error detection and network analysis features of the algorithm are also described.Keywords
This publication has 4 references indexed in Scilit:
- PERT time calculations without topological orderingCommunications of the ACM, 1965
- Resource allocation and multi-project scheduling (RAMPS)--a new tool in planning and controlThe Computer Journal, 1963
- Critical-Path Planning and Scheduling: Mathematical BasisOperations Research, 1961
- Application of a Technique for Research and Development Program EvaluationOperations Research, 1959