A Model for Master Production Scheduling in Uncertain Environments
- 1 July 1992
- journal article
- Published by Wiley in Decision Sciences
- Vol. 23 (4) , 839-861
- https://doi.org/10.1111/j.1540-5915.1992.tb00422.x
Abstract
In uncertain environments, the master production schedule (MPS) is usually developed using a rolling schedule. When utilizing a rolling schedule, the MPS is replanned periodically and a portion of the MPS is frozen in each planning cycle. The cost performance of a rolling schedule depends on three decisions: the choice of the replanning interval (R), which determines how often the MPS should be replanned; the choice of the frozen interval (F), which determines how many periods the MPS should be frozen in each planning cycle; and the choice of the forecast window (T), which is the time interval over which the MPS is determined using newly updated forecast data.This paper uses an analytical approach to study the master production scheduling process in uncertain environments without capacity constraints, where the MPS is developed using a rolling schedule. It focuses on the choices of F, R, and T for the MPS. A conceptual framework that includes all important MPS time intervals is described. The effects of F, R, and T on system costs, which include the forecast error, MPS change, setup, and inventory holding costs, are also explored. Finally, a mathematical model for the MPS is presented. This model approximates the average system cost as a function of F, R, T, and several environmental factors. It can be used to estimate the associated system costs for any combination of F, R, and T.Keywords
This publication has 19 references indexed in Scilit:
- Freezing the Master Production Schedule Under Demand UncertaintyDecision Sciences, 1990
- Notes and Communications REPLANNING FREQUENCIES FOR MASTER PRODUCTION SCHEDULESDecision Sciences, 1986
- Planning horizons for master production schedulingJournal of Operations Management, 1984
- A Lot-Sizing Algorithm for Reducing Nervousness in MRP SystemsManagement Science, 1984
- The impact of a rolling schedule in a multi‐level MRP systemJournal of Operations Management, 1982
- A NOTE ON DYNAMIC LOT SIZING IN A ROLLING‐HORIZON ENVIRONMENTDecision Sciences, 1982
- THE EFFECTIVENESS OF EXTENDING THE HORIZON IN ROLLING PRODUCTION SCHEDULINGDecision Sciences, 1982
- HEURISTIC LOT‐SIZING PERFORMANCE IN A ROLLING‐SCHEDULE ENVIRONMENT*Decision Sciences, 1980
- Less Nervous MRP Systems: A Dynamic Economic Lot-Sizing ApproachManagement Science, 1979
- AN EXPERIMENTAL STUDY OF THE EFFECTIVENESS OF ROLLING SCHEDULES IN PRODUCTION PLANNINGDecision Sciences, 1977