Abstract
The results of field tests on a buried, 34-inch diameter gas pipeline adjacent to a 525 kV ac power transmission line for 54 miles are discussed. Comparison is made between measured inductive coupling data and predictions obtained using the theory developed in part I of this paper. An excellent agreement of the predicted and measured results is shown for the location and magnitude of all induced voltage peaks on the pipeline.

This publication has 0 references indexed in Scilit: