A heuristic scheduling algorithm for improving the duration and net present value of a project
- 1 January 1995
- journal article
- Published by Emerald Publishing in International Journal of Operations & Production Management
- Vol. 15 (1) , 89-98
- https://doi.org/10.1108/01443579510077241
Abstract
Proposes a heuristic iterative scheduling algorithm for the resource constrained project scheduling problem. Considers a general model where activities are represented by multiple operating modes and each operating mode is constituted of different activity durations and resource requirements. The performance measures considered are the minimization of project duration and the maximization of net present value (NPV). In the cash flow model assumed, activity expenditures take place at their start times and the project payment is made on its completion. The iterative scheduling algorithm consists of forward/ backward scheduling passes, where consecutive scheduling passes are linked by updated activity time windows. The iterative algorithm is supported by a conflict‐based activity selection technique called local constraint based analysis (LCBA). A considerable amount of improvement in both performance criteria is observed when the results of the iterative algorithm are compared with the results given by the initial forward schedule.Keywords
This publication has 23 references indexed in Scilit:
- A constraint-based perspective in resource constrained project schedulingInternational Journal of Production Research, 1994
- Computational experience with a backtracking algorithm for solving a general class of precedence and resource-constrained scheduling problemsEuropean Journal of Operational Research, 1990
- The scheduling of activities to maximize the net present value of projectsEuropean Journal of Operational Research, 1990
- Some efficient multi-heuristic procedures for resource-constrained project schedulingEuropean Journal of Operational Research, 1990
- Heuristic Performance and Network/Resource Characteristics in Resource-constrained Project SchedulingJournal of the Operational Research Society, 1989
- USING A LATE‐START RESOURCE‐CONSTRAINED PROJECT SCHEDULE TO IMPROVE PROJECT NET PRESENT VALUE*Decision Sciences, 1987
- Multiobjective network scheduling with efficient use of renewable and nonrenewable resourcesEuropean Journal of Operational Research, 1981
- Two Approaches to Problems of Resource Allocation Among Project Activities — A Comparative StudyJournal of the Operational Research Society, 1980
- Multiple Resource–Constrained Scheduling Using Branch and BoundA I I E Transactions, 1978
- Scheduling a Project Under Multiple Resource Constraints: A Zero-One Programming ApproachA I I E Transactions, 1976