Line‐of‐Balance Scheduling in Pavement Construction

Abstract
Linear Scheduling Methods are best suited to projects that display repetitive characteristics, but their use in the construction industry is limited. Line‐of‐Balance (LOB) is a Linear Scheduling Method that also makes use of network technology. Its benefits and shortcomings are investigated in a high‐way surface treatment project where LOB has been used experimentally. It was determined that LOB is extremely sensitive to errors in man hour, crew size, and activity duration estimates. There are also problems of a visual nature with the presentation of the diagram. On the other hand, LOB allows a better grasp of the project than any other scheduling technique because it is possible to adjust activities' rates of production. It provides a smooth and efficient flow of resources and requires less time and effort to produce than network schedules. Research to make Linear Scheduling Methods more attractive is recommended.

This publication has 17 references indexed in Scilit: